Still no windows. They were promised by Nordan on Monday, then Tuesday, then Thursday. And now, the fitter has apparently told Kevin that they would be delivered tomorrow morning and fitters would be over later in the day. Very frustrating. We'll have lost a week because of this.
In the meantime, we have discovered what appears to be a leak - two of the rafters in the roof are wet. We're not sure if there is a leak with water going down or if water is going back up the rafters by capillarity, i.e. from the bottom up. My guess is that it's going up from the bottom, as we can't find any source for a leak. We'll talk to Kevin about it in the morning. In the meantime, there is nothing we can do about it. At least it's come to light now, before the ceiling is insulated and plastered. If it was a dry summer, this would not have come to light until a few months later, so we're lucky I guess. Thank god for a wet summer!